Shell TGU project

Visser & Smit Hanab BV was awarded the contract for the complete revamp of two large furnaces in the Thermal Gasoil Unit. The works were to be planned and performed in the shortest possible timeframe including several heavy lift operations and demolition of contaminated plant sections.

Our activities consist of:

  • Works preparation, Works- and QC-procedures and Construction Engineering.
  • Partly demolition of existing TGU-plant
  • Re-instating remaining sections
  • Installation of new Heated-Surface
  • Re-installation of fluegas ducts and -casings

The works were prepared during a 4 months period in which joint Construction Review Meetings were held with the client and suppliers in which the Construction Engineering and -Plans were reviewed and subsequently revised. Special attention was paid to the numerous heavy lifts in a small Construction Area, and the works on possibly contaminated plant. The result was a Construction Project that was planned and prepared to the highest possible detail, leaving no surprises but only a professional challenge.

Our added values:

  • Timely delivery of the works in 28 days after starting the works
  • Zero-defect site installation of pressure- and non-pressure parts
  • Zero-accident site installation
  • Integrated planning with contractors of different trades